LPC meeting summary 23-10-2023 - final |
![]() |
Main purpose of the meeting: Meeting dedicated to the current ion run
Filip (Introduction)
Slide 5:
Roderik still to discuss with MPP regarding the limit of number of bunches for the Beam-Beam MD
BFPP quench test will include a dump and refill. No Stable Beams foreseen. Filling scheme should be the same as the one in physics production in the last night.
Slide 6:
Electricity cuts only impact 4 weeks of operations wrt to the 6 weeks of 2023.
Andrea (CMS)
Slide 2:
4 emittance scans are per individual fills
15 points may be preferred
ATLAS requested 2 emittance scans until the end of the year. Preferred that if they are done with 15 points, the ATLAS scan should be done together with CMS one.
Silvia (ATLAS)
Slide 2: not to forget that the crossing angle for ATLAS/CMS should be the same as in 2023
Niels (LHCb)
Slide 2: decision on sharing of number of bunches will be passed to the Director of Research who will mediate
Sarah (ALICE)
Slide 3:
Plan is to continue with physics production until the end of the week. Filling schemes may change based on negotiations and decisions.
Next meeting on November 6th, with first requests/scheduling discussion for 2024.