CERN

LPC meeting summary 27-11-2017 - final

Minutes overview      LPC home


Minutes and Summary

Main purpose of the meeting: The end of the 2017 data taking period is summarised. An update of possible running scenarios for 2018 is given. Afterwards feedback from the experiments for Evian 2017 is discussed.

Introduction (Jamie Boyd)

Jamie summarised the end of the 2017 data taking period. The year has been very successful for most of the foreseen runs. The pp run ended with 50 fb-1 delivered to ATLAS and CMS and 1.86 fb-1 to LHCb. It was possible to acquire more than 170 hours of Stable Beams (160 hours requested) in the 5 TeV pp reference run for ALICE in parallel to largely sufficient luminosity delivered to the other experiments. The run ended with a very efficient low μ data taking programme at 13 TeV for ATLAS ad CMS (80 hours acquired) during which LHCb could enlarge their standard pp data sample. 

Jamie congratulated the injector chain the LHC and the technical teams as well as the experiments to this success.

The low μ data sample was taken with ATLAS leveled to μ=2 and CMS to μ=3. No big problems from instabilities were encountered due to the fact that all experiments had the beam separated. The bunch intensities in this run were reduced to 1e11 ppb which allowed an accelerated ramp-up. In some of the runs some bunches blew up which lead to higher pileup in these bunches due to the fact that for these bunches the separation was reduced due to the blow-up.

For the high β* low energy run another test has been executed on Wednesday. This test revealed that off-momentum background plays an important role in the bad background conditions. Although it was possible to achieve some improvements wrt previous tests it is not clear if any configuration tested could be used for physics data taking. This will only be clear after an offline analysis of the available data. Therefore it was confirmed that the decision to cancel the run for this year was correct.

 

Topics for preparation of the 2018 run (Christoph Schwick)

Christoph introduced the discussion for the 2018 data taking period by showing the current draft schedule for 2018 pointing out its main features.

He then showed the integrated luminosities acquired by the experiments during Pb-Pb runs up to now (at 2.5 Z TeV during run I and at 6.37 Z TeV in 2015). In order to guide the expectations he stated that a good starting point would be to consider the best runs in 2015 which were run 4717 and run 4720. John Jowett informed the LPC that in 2018 only minor improvements wrt 2015 could be expected. For example in the p - Pb run in 2016 the maximum Pb intensity achieved was 2.1e8 ions/bunch instead of 1.96e8 ions/bunch in 2015. Filling schemes still need to be developed and it is not yet clear if and how much these can improve the performance of the 2018 run.

Christoph then gave an update on the maximal cryo load of the machine. Precise recalibration of the cryo load in 4 sectors have been performed by the experts and presented in the LMC of the 21st of June. In all 4 sectors the maximal allowed heat-load was measured to be higher than expected before. However 4 sectors have not yet been re-measured. Among these is also sector 1-2 which has the highest heat-load in the machine and which in addition will be warmed up in the YETs to cure the problem in 16L2. But the encouraging measurements in the 4 other sectors give hope that intensities of 1.3e11 ppb in the BCMS scheme could be achievable. 

Christoph then showed a possible example scenario based on 25ns BCMS with either β* leveling as discussed so far (four discrete steps of β*: 40cm, 37cm, 33cm, 30cm with a fixed crossing angle of 150μrad), and compared it to an equivalent scenario applying leveling by separation.  The differences in integrated luminosity for both scenario after a running time of 12 hours are negligible. However where β* leveling is using fixed configurations of β* and the crossing angle in the first part of the fill, separation leveling gives more flexibility since it can be changed at any time by the experiments if desired. The complication of β* leveling for the forward physics experiments is discussed later.

Feedback from the experiments and discussion

ALICE (Kristjan Gulbrandsen)

pp run

ALICE was asked by the LPC if they would accept to run at β* of 2m instead of 10m if this could simplify and shorten the commissioning of the Heavy Ion run. ALICE replied that they would not object to this if they could still be leveled to the desired luminosity stably. Jörg Wenninger remarked that this would imply the development of a completely new Ramp and Squeeze which would prolong the commissioning. In addition the separation of the beams in ALICE would become so large that after every fill start one would have to "search" for the collisions in ALICE which would take time. This would lead to a luminosity loss in ALICE.

VdM scan

ALICE considers a change in crossing angle for the VdM scan in the pp run in order to be able to use the ZDC.

PbPb run

The LPC commented that these numbers are hard to understand if the details of the ALICE trigger and data acquisition system are not known. ALICE should present their expectation as a number in terms of delivered luminosity (of course motivated by the physics they want to achieve).

It was further remarked that this expectation would probably mean that ALICE expects at least 750 μb-1 of delivered luminosity. Considering the facts mentioned by Christoph about the Pb run in 2018, it is hard to see how such a goal can be achieved.

The LPC concluded that they would follow up with ALICE on one side and John Jowett on the accelerator side.

ATLAS (Masaya Ishino)

pp running

Special runs

HI run

CMS (Silvia Goy-Lopez)

pp-running

Special runs, luminosity related requests

Pb Pb run

LHCb (Niels Tuning)

pp running

Special runs

Pb Pb run and e-p test run

TOTEM (Mario Deile)

90m-like run

low energy high β* run

TOTEM is in principle interested in this run but a possible future request for this will depend on the offline analysis of the data taken in various tests this year.

Jamie urged TOTEM and ATLAS/ALFA to work out a common schedule for the next steps to come to a decision on whether or not to request the low energy high β* run. Such a run needs to be put into the plan at an early stage and therefore a decision for the request needs to be made soon.

pp running and β* leveling in CTPPS

An open question is if for this scenario an acceptable fixed position of the pots can be found or if the pots will have to be move for the different β* steps. Further analysis is needed to answer this question.

In general CTPPS prefers if β* leveling will NOT be introduced in 2018 but they do not explicitly request this.

Jörg indicated that the machine experts are working on alternative β* leveling scenarios which will be presented in Evian.