LHC Commissioning Plan 2016 |
Date | Task | Details |
---|---|---|
18/03/2016 | Test of Beam flags |
Various tests are planned during the 15h00 shift:
|
21/03/2016 | TED shots in IP 2 and 8 |
|
22-23/03/2016 | All experiments closed. |
From now on only controlled access allowed to the experimental caverns. This means access needs to be requested via e-mail to Rossano Giachino and the access will be discussed in the daily 8h30 meetings. |
Easter | First commissioning with beams |
First probe bunches will be inserted into the LHC and threaded through the machine. Of the order of one/afew splash(es) is/are expected in the experiments during this operation. The machine-mode will be "Setup Beam", the beam mode will be "Injection Probe Beam". |
29/03/2016 | Splash events for ATLAS/CMS |
A series of SPLASH events (O(10) per side) will be given to the experiments ATLAS and CMS for commissioning purposes. (bucket 1 for beam-1 and 2001 for beam-2; starting around 10:30 am) |
2016-03-31 | Magnets of ALICE and LHCb switched on. |
To further commissioning LHC the Dipoles of the experiments need to be switched on to control and correct the kicks due to the magnetic fields during the various phases of the machine cycle. |
2016/04/08 | Collisions during setup of the TCTs |
The beams will be ramped. These collisions can be used parasitically by the experiments, 2 nominal bunches colliding in each IP (+ a few probes non-colliding). Relative luminosity information requested by experiments. |
2016/04/11 | Quiet beams with collisions to determine IP position |
Experiments try to determine the IP position and give feedback to the machine within 24h. The quiet beam will be done with aligned TCTs. The settings are not yet validated with loss maps. The beam will be ramped and squeezed with 3 nominal bunches. |
2016/04/13 | Quiet beams with collisions. |
This exercise is before a shutdown of the injectors. Filling will start in the night around 4am. Quiet beams will be finished probably around 10h00. CMS will repeat the exercise to separate the beams after one hour of quiet beams for approx. 30min. This will allow to see if the difference in z-position of the beamspot which was observed in the quiet beams on the 11th of April can be reproduced or not. ALICE also wants to run some time with beams separated. |
2016-04-17 | Aperture checks in IP1 |
These checks re-measure and, if necessary, address the limitation in B1V on the L side of IP1. |
2016/04/18 | Collisions for TOTEM / AFP (?) after Roman pot alignment (same fill) |
Details to be defined. |
2016/04/25 | First Stable Beams. |
The intensity ramp up for 2016 starts. After three days a scrubbing run for four days is foreseen. |
2016/05/04 - 2016/05/08 Ascension long-weekend |
Intensity ramp-up |
|
2016/05/17 - 2016/05/18 | VdM scan. |
VdM scans for 2016 data taking. Two days are foreseen for the completion of the scans. Details of the setup are availble in this talk. Proposed filling schemes: Multi_51b_8_27_16_4bpi14inj_alt (for IP2/8 scans), Multi_56b-52b_32_16_8_4bpi14inj (for IP1/5 scans). |
2016/05/27 | VdM scan.2 |
VdM scan for CMS (and one scan for ATLAS). |
2016/06/07 - 2016/06/09 | (reduced) TS 1 |
Technical Stop 1, followed by 2 days for re-commissioning/validation. |
2016/06/09 | AFP / collimator test |
3b fill where the effect of different AFP/TCL settings on the ALFA radiation will be studies ~2hrs. |
2016/06/10 | mu-scan (IP1/5) |
mu-scan in IP1/5 (+/-2sigma per beam in out-of-crossing-plane). (~45mins each not at same time). (requires 2 isolated INDIVs in filling scheme). |
2016/06/10 | MD1224 |
Beam background pressure test MD for IP1/5/2 (602b filling scheme). (same fill as above). (During stable beams). (~3hrs). |
2016/06/16 | Setup β* 2.5km |
The first day dedicated to set up the 2.5km β* run. Will probably include 2hrs of tests of background for TOTEM/ALFA as a function of collimator positions. |
2016/09/25 - 26 | Intensity ramp-up after TS2 (crossing angle change) |
|