CERN

Configurations for Special Runs / VdM in 2018

LPC home

LPC: 79977

The data shown here is "work-in-progress"

 

The parameters on this page reflect the best current knowledge and will be regularly updated and changed accordingly. Please consider this when using these parameters for any estimate. In case of doubts do not hesitate to ask the LPC.

 

 

 

Contents

 

VDM scan 2018

90m run

Low E high ß* run

 

 

 

 

AGK after TS1

After TS1 up to and including the 90m run the AGK should be adjusted to 31271

Afterwards it will be reverted to the standard 32811 for this years physics production

VdM programme 2018

The VdM programme is scheduled to start after the 3b validation fill after TS1. This will probably fall on the weekend of the 23/6/2018 24/6/2018. The programme consists of the following steps (no turn-around times taken into account here).

Maximum separation allowed by MPP: 2.5 nominal σ for each beam in one plane at a time. Separation in both planes at the same time are not allowed. The limits are given in terms of nominal emittance : εn=3.5µm. This means that the de-facto separation is larger since we in fact run with lower emittance (~2.3µm). 

Step Duration Experiments activities Remarks
3b validation fill 30min  
ATLAS CMS MPP
head-on head-on
4min : emittance scan
Go to Stable beams; verify crossing angle and ß* anti-leveling; RP insertion

 

30min Stable Beams for MPP with crossing angle and beta star anti leveling

 

Calibration transfer fill (150b) 4.5h  
ATLAS CMS MPP
2h   : immediate beam separation to µ=0.5 after optimisation head-on CMS 1h head-on
RP insertion
0.5h: maximal beam separation
1h   : µ-scan
1h   : head-on 45min : µ-scan ATLAS 1h head-on

 
Filling Scheme:
Multi_525ns_140b_140_75_16_8bpi_19inj.csv
Scheme optimised for few AGK changes
No crossing angle or ß* anti-levelling
600b 2.5h
 
 
ATLAS CMS MPP
1h : head on emittance scan and 0.5h trigger tests with 3 different separations 1h head-on each IP
RP insertion
> 2h total
2h head-on
1.5h : at µ=0.3 (AFP/HI)

 
Filling Scheme:
25ns_603b_590_524_542_48bpi_17inj
1200b 8h  
ATLAS CMS MPP
1h : immediate max. separation
       then µ-scan

8h head-on

µ-scan (45min) when ATLAS is head on

1h head on each IP
RP insertion;
crossing angle anti-levelling (but not during µ-scans)
> 5h total
1h : head-on (MPP)
5h : µ=0.3 (AFP / HI)
1h : head-on during ß* leveling ß* anti levelling at the end

 
Filling Scheme:
25ns_1227b_1214_1054_1102_144bpi_14inj.csv
2460b 8h  
ATLAS CMS MPP
1h : head-on and emittance scan 8h : head-on

emittance scan when ATLAS is head on
1h head-on each IP
RP insertion
crossing angle anti-leveling (but not during µ-scan)
>5h in total
1h : µ-scan
6h : µ=2 (W pt measurement)
head-on ß* anti-levelling

 
Filling Scheme:
25ns_2460b_2448_2052_2154_144bpi_19injv2.csv
 
Scans IP2/8

8h45min
(plus overhead)

 
LHCb ATLAS ALICE
1h : LHCb part 1    
  2h : ATLAS Length scale calibration  
2h15min : LHCb part 2     
    3h30min : ALICE scan

 

Filling Scheme:
Multi_70b_58_20_22_4bpi_19inj.csv

Scans IP1/5

15h45min
(plus overhead)

 
ATLAS CMS
1h : ATLAS part 1  
  3h30min : CMS part 1
3h : ATLAS part 2 (non-factorization)  
  1h30min : CMS part 2
2h : ATLAS part 3  
  3h30min : CMS part 3
1h ATLAS part 4  
  15min : CMS emittance scan & super separation
(6 sigma total in x/y)

 

Filling Scheme:
525ns_140b_124_32_23_16bpi_11inj.csv

ATLAS 1 2 and 3 4 need to be in same fill

CMS: 1 and 2 need to be in same fill
if beam is lost in cms part three, we need to refill

Sandwich fill 2460b 3h or more:
adapted to start of 90m run
 
ATLAS CMS
1h : max separation with µ-scan  
2h : head-on with emittance scan (after CMS) 15min : emittance scan
head-on as long as adequate to start 90m programme; emittance scan before dump  

 
Filling Scheme:
25ns_2460b_2448_2052_2154_144bpi_19injv2.csv

After this programme the 90m special run with be started.

 

 

Beam parameters for Calibration Transfer fill

Items Remarks
Filling Scheme Multi_525ns_140b_140_75_16_8bpi_19inj.csv
Bunch Spacing 525 ns (minimal)
Injections up to 2 batches of 4 bunches
Emittance in Stable Beams tolerable variations: 2µm to 3µm
Intensity in Stable Beams 1.2x1011 ppb  --  tolerable variations: 1.1x1011 ppb to 1.25x1011 ppb; 
Brightness (bunch intensity / emittance) < 0.5 x 1011 ppb / µm

 

Beam parameters for Scans in IP2 and IP8

Items Remarks
Filling Scheme Multi_70b_58_20_22_4bpi_19inj.csv
Bunch Spacing 1000 ns (minimal)
Injections up to 4 batches of 1 bunch ("traditional" VdM schemes)
Emittance in Stable Beams 3µm for LHCb;  >3µm for ALICE (second in scan programme)
Intensity in Stable Beams 0.7x1011  - 0.9x1011 ppb in LHCb
0.4x1011  - 0.9x1011 ppb in ALICE (Alice is second in the scan programme)
Profiles Preparation for VdM : Gaussian profiles which factorise the beam wrt H and V planes
IP 8 Dipole polarity + / +
IP 8 external half crossing angle  145 µrad; internal half crossing angle : -75 µrad --> effective half crossing angle at IP: 70 µrad which is ok for using the ZDC.
Injection Optics With crossing angle to not have problems with LR interactions when beams are large at injection
IP2 polarities + / + (Dipole and L3 magnet)
IP2 internal crossing angle -75µrad
IP2 external crossing angle 145 µrad
IP2 effective crossing angle +70µrad
IP2 y - vertex shift -1 mm

 

Beam parameters for scans in IP1 and IP5

Items Remarks
Filling Scheme 525ns_140b_124_32_23_16bpi_11inj.csv
Bunch Spacing 525 ns (minimal)
Injections up to 4 batches of 4 bunches
Emittance in Stable Beams 3µm -- tolerable variations: 2µm to 4µm; some spread O(20%-30%) is welcome
Intensity in Stable Beams 0.85x1011 ppb  --  tolerable variations: 0.70x1011 ppb to 0.95x1011 ppb;  some spread O(20%-30%) is welcome
Profiles Preparation for VdM : Gaussian profiles which factorise the beam wrt H and V planes
IP 8 Dipole polarity + / +
IP 8 external half crossing angle  145 µrad; internal half crossing angle : -75 µrad --> effective half crossing angle at IP: 70 µrad which is ok for using the ZDC.
Injection Optics With crossing angle to not have problems with LR interactions when beams are large at injection
BGV measurements Requested by CMS (to be followed up by LPC)

 

90m run at high luminosity

The 90m run is scheduled for taking place after the VdM programme scheduled after TS1.

The squeeze for this fill will be very long (40m).

The 90m programe starts with the 100ns beam. This beam will be used until ATLAS has collected 0.5/pb at a pileup of 0.1 ... 0.15. This needs approx. 10 hours.

Items Remarks

Ramp - up
100ns beam

At least 2 hours SB, expert check heat load
Fill 1 : 100ns_86b_84_0_0_18bpi_7inj.csv
Fill 2 : 100ns_302b_300_0_0_72bpi_7inj.csv
Fill 3 : 100ns_734b_732_0_0_72bpi_13inj.csv (production scheme)
The schemes use batches with 12 and 18 bunches. The 12b train is used as first train for steering and MPP.

Ramp - up
50ns beam

At least 2 hours SB, expert check heat load
Fill 1 : 50ns_302b_300_70_63_72bpi_7inj.csv
Fill 2 : 50ns_734b_732_284_398_144bpi_11inj.csv
Fill 3 : 50ns_1452b_1450_21_1128_144bpi_11inj.csv (production scheme)
The schemes use batches with 12 and 18 bunches. The 12b train is used as first train for steering and MPP.
Bunch spacing 100ns and possibly 50ns
β* in IP1 90m
β* in IP5 β*x=45m ;  β*y​​​​=90m  --> ßeff = 64m
εn 1,2µm - 1.6µm (1.2µm is hoped for by the physics comunity. J. Wenninger remarked that there will be probably some blow-up in the ramp)
half crossing angle 50μrad; to be seen if the crossing angle in IP1 can be increased if enough corrector strength available
   

Expected Luminosities

Most of the values below are assuming conservatively an emittance of 1.6µm

With the values below it is expected that we need to run 8.2 hours with 100ns with the full 100ns scheme before going to 50ns. (The 100ns ramp up will result in approximately 0.56pb for ATLAS)

bs [ns] n-colliding I (ppb) εn [µm] half c-angle [µrad] ßeff [m] sep [µm] µ Lumi Remark
100 732 1.0x1011 1.2 50 64 0 0.57 5.92x1031 emittance too low
100 732 1.0x1011 1.6 60 64 0 0.43 4.44x1031 0.16 pb/h
100 732 1.0x1011 1.6 60 90 310 0.15 1.55x1031 0.058 pb/h
                   
50 1450 0.8x1011 1.6 60 64 0 0.28 5.6x1031 0.20pb/h
50 1450 0.8x1011 1.6 60 90 0 0.20 4.0x1031 0.14pb/h
                   

 

 

Low E high ß* special run at injection energy

This special run is planned to have three components: 

  1. Data taking at injection energy and high ß* to measure the elestic cross section at low t (with pots at 3 σ)
  2. A VdM scan (requested by ATLAS/ALFA) at injection energy using injection optics without crossing angle
  3. A short physics run at ß*=11m (requested by TOTEM) using injection optics to cover the higher t-range. (Pots will be moved close to the beam)

Data taking at 900GeV cms and high ß*

The programme foresees to use the collimation configuration tested successfully on Tuesday the 2nd of October. It was agreed that towards the beginning of the data taking programme (but during day time since experts need to be available) also one or two runs with the crystal collimation scheme should be taken. TOTEM considers this scheme even favourable since they observed a smaller (almost no) growth of the background rates with a very high Signal to Noise ratio. However ALFA observed that the background is distributed such that it is more difficult ot separate from the signal than in the "standard" collimations scheme and therefore does not want a significant fraction of data to be taken with crystal collimation. ALFA welcomes to take one fill with crystal collimation anyway. 

Luminosity requests

TOTEM requests to take an integrated luminosity comparable to that taken in the 2.5km run in 2016: 380µb-1.

ALFA requests to take 106 elastic events. This should correspond to an integrated luminosity around 400µb-1

Therefore the requests of both experiments are compatible with each other.

Beam conditions 

For the bunch intensities a trade off between luminosity per bunch and background conditions has to be found. The aim is to maximise the luminosity with clean background conditions. During the collimaition test it was found that when increasing the initial bunch intensity to close to 1e11 ppb the background conditions after the first scraping have been bad whereas after a second scraping they were excellent. However these two scraping processes cost 20% luminosity drop each, hence a 40% luminosity loss. It has therefore been decided to go for more moderate beam intensities and more bunches which should allow data taking after one scraping process. 

It was further agreed that one should try to inject higher intensities (0.9e11-1e11) with the first 5 bunches and then scrape these bunches down until another 1 or  2 bunches can be injected. Then one more scraping would be performed. With the experience of the test this could lead to very clean conditions at reasonably high luminosity (up to 40% higher than the first data taking period with 5 bunches during the test)

It has been agreed that at the beginning of the data taking some experimentation with the beam parameters / scraping procedures might be performed. However it should be avoided to continuously change the requested intensities from the injectors and once a good configuration has been found, the physics data should be taken with that configuration until the requested luminosity is acquired. 

 

Items Remarks
No bunches 6 or 7
Non colliding bunches 2 fills with 1 non-colliding bunch to be taken towards the start and the end of the data taking period.
Intensity per bunch at injection 0.9 - 1 x 1011 ppb (see remark above)
Initial Intensity when taking data (after scraping) ~0.6 x 1011 ppb 
Emittance ~1.2µm
ß*eff TOTEM 84m
ß*eff ALFA 70m
   
   

Performance estimates

Two independent estimates have been performed based on observations during the test run. Using beam parameters and lumi calculator one can do the following (conservative) estimate:

Intensity per bunch: 0.55 x 1011 ppb
Average emittance: 1.2µm (taking into account some emittance growth during a fill. The initial emittance has been observered to be around 1µm)
Lumi per bunch at TOTEM (ß*=84m) : 1.3 x 1027
 

collisions lumi T400µb [h] Lumi drop and duty cyle
(120min data / 30min filling)
factor 0.65 [h]
Lumi per hour [µb/h] 70% availability [h]
5 6.5 x 1027 s-1cm-2 17.1 26.3 15.2 37.6
6 7.7 x 1027 s-1cm-2 14.4 22.2 18.0 31.6
7 9.0 x 1027 s-1cm-2 12.3 18.9 21.1 27.0

From the rates seen in ALFA a similar esimtation can be performed: ALFA saw an elastic rate of the order of 9Hz in each arm resulting in a total of 18Hz elastic events. To reach 106 elastic events at 18Hz, 15.4 hours are needed. Considering the lumi drop and duty cycle (factor 0.65) and 70% availability this results in 33.8 hours which is compatible with the above estimates within the errors.

VdM scan (1st try)

The VdM scan will be performed with injection optics but taking out the crossing angle bumps. The filling patteren with contain as many bunches as possible at 525ns bunch spacing. 2 non-colliding bunches will be injected. 

LHCb is able to measure ghost charge. 

Item Remarks
Filling scheme Multi_525ns_152_150_0_0_8bpi_19inj.csv
Optics Injection optics without crossing angle bumps
Crossing angle 0
ß* 11m
Transverse emittance 1.5µm - 2.5µm in the LHC at the start of the (Note: 1.8µm is the minimum emittance if the brightness limit and the intensity limits should be respected)
Intensity 1.2e11 -- 1.4e11 ppb
Brightness < 0.65 x 1011 ppb/µm (This is a hard criteria)
Others Special VdM scraping treatment for gaussian shape and factorisation of beam profiles
Injections 2 batches of 4x1b spaced by 525ns; batch spacing also 525ns

 

VdM scan (2nd try)

The first VdM scan performed during the special run suffered from a very high ghost and satellite contribution. In addition a technical problem in LHCb prevented most of the data of the SMOG ssytem to be recorded to measure these contributions precisely. This will lead to a high systematic uncertainty for the luminosity. Therefore, if possible, a second try for this scan will be performed during the recovery of the Ion source problem after TS3. Changed parameters will be signalled in red.

The VdM scan will be performed with injection optics but taking out the crossing angle bumps. The filling patteren with contain as many bunches as possible at 525ns bunch spacing. 2 non-colliding bunches will be injected. 

Again LHCb will kindly provide ghost charge measuremnts with their SMOG system.

Item Remarks
Filling scheme Multi_525ns_152_150_0_0_8bpi_19inj.csv
Optics Injection optics without crossing angle bumps
Crossing angle 0
ß* 11m
Transverse emittance 1.5µm - 2.5µm in the LHC at the start of the fill
Intensity max 1.0e11 ppb
Brightness < 0.65 x 1011 ppb/µm (This is a hard criteria)
Others Special VdM scraping treatment for gaussian shape and factorisation of beam profiles
Injections 2 batches of 4x1b spaced by 525ns; batch spacing also 525ns
RF cavity voltage Increased to 12 MV (RF experts consider blow-up after injection)
Scan programme Duration 2.5h to 3h; has to start immediately after the filling
Abort Gap Cleaning Active during the entire programme or at least between the various scans
(to be discussed with ATLAS)

 

 

ß* = 11m run

This run has been requested by TOTEM in order to extend the acceptance in the higher t range. It is assumed that an equivalent luminosity of 400µb should be taken. Due to the optics having ß*=11m a factor of 7 in luminosity is expected wrt the low E high ß run. Hence the data could be taken in O(3h) assuming 100% availability.

It was decided that a 2 stage collimation system should be set up for this run. This will be done directly before the data will be taken.  


This web site is owned by the account lpc .