CERN

Configuration for the proton-lead-run 2016

LPC home

LPC: 79977

Disclamer

The data in this table has been compiled in collaboration with the HI machine experts (especially Michaela Schaumann helped to fill this table with interesting contents). This document is work in progress and will be updated whenever needed or useful. 

 

General remarks

5 TeV run

Experiments requests

     
IP1 (ATLAS)
Min bias events A few kilohertz Achievable with a few colliding bunches
LHCf data taking   With pileup limited to ???; to prepare for the 8 TeV run
IP2 (ALICE)
Luminosity 0.3-0.6x1028cm-2s-1 Was higher before (1.0 x 1028). Minimum number of bunches for pileup 0.5% is 106-213
Minimal number of events 679M assuming 1.5kHz readout rate (was 2kHz before) and 86% efficiency (LHC and ALICE) : need 6 days
Desired number of events 1000M assuming 1.5kHz readout rate (was 2kHz before) and 86% efficiency (LHC and ALICE) : need 9 days
Beam direction Protons in beam 1  
IP5 (CMS)
Min bias events O(10kHz) Achievable with a few colliding bunches
IP8 (LHCb)
Min bias data   Running with low pileup
Beam direction Protons in beam 1 Compatible with ALICE request.

LHC configuration

     
General beam properties
Beam energy 4Z TeV (5.02 TeV cms)
Ion beam intensity 1.4x108  
Proton beam intensity 2.0x1010  
Ion beam emittance 1.3 - 1.5 µm  
Proton beam emittance 2.2 µm  
Ion beam bunch length 0.09m depends on the blow up which will be set
Proton beam bunch length 0.09m depends on the blow up which will be set
RF voltage 14MeV  
β beating 1.5% from simulations
Peak lumi per bunch 2.6x1025cm-2s-1 At IP1/5 with β*=11m; being optimistic could be a factor of 2 better.
IP1/5 (ATLAS/CMS)
β* 11m  
Half crossing angle 140µrad  
Geometric Factor protons 0.986  
Geometric Factor ions 0.991  
Peak lumi estimate 3.7x1026cm-2s-1 Assuming 14 colliding bunches. Being optimistic could be a factor of 2 better.
IP2 (ALICE)
β* 2m implemented as "Ramp & Squeeze"
Leveling factor ≈20  
Geometric Factor protons 0.985  
Geometric Factor ions 0.991  
Peak lumi estimate 6.4x1028cm-2s-1 Assuming 443 colliding bunches. Theoretical peak lumi if ALICE would not be leveled.
External crossing angle +185 µrad  
Internal crossing angle -122.5 µrad  
Total half crossing angle 63 µrad  
Magnet polarity + / +  
IP8 (LHCb)
β* 10m  
Geometric Factor protons 0.864  
Geometric Factor ions 0.908  
Peak lumi estimate 5.7x1026cm-2s-1 Assuming 22 colliding bunches.Being optimistic could be a factor of 2 better.
Dipole polarity positive  
External half crossing angle -230µrad  
Internal half crossing angle -236µrad  
Half crossing angle -466µrad  

Filling schemes

Scheme  
100_200ns_702p_548Pb_0_480_0_20inj Maximal amount of collisions in ALICE. Will be used if problems with other schemes are encountered.
100_200ns_702p_548Pb_27_458_0_20inj  
100_200ns_702p_548Pb_0_458_22_20inj  
100_200ns_702p_548Pb_14_443_22_20inj Default scheme with some collisions at all IPs.

8 TeV run

Experiments requests

     
IP1 (ATLAS/LHCf)
Integrated delivered luminosity 100/nb  
VdM scan   One for each beam direction
LHCf run lumi: 1028cm-2s-1 It is being discussed if the LHCf run can take place at the end of one or multiple high lumi runs.
IP2 (ALICE)
Luminosity 1029cm-2s-1cm-2s-1 Can read out at 300kHz.
Delivered Lumi 20/nb  
VdM scan   One for each beam direction
IP5 (CMS)
Integrated delivered luminosity 100/nb If 70nb will be delivered this is still acceptable. Less would compromise the physics goals.
VdM scan   At least one with the first beam configuration. Will decide later if a second will be requested during the second part.
IP8 (LHCb)
Integrated delivered luminosity 20/nb  
Beam reversal   Equal lumi in both configurations.
VdM scan   One for each beam direction

LHC configuration

     
General beam properties
Beam energy 6.5Z TeV (8.16 TeV cms)
Ion beam intensity 1.4x108  
Proton beam intensity 2.0x1010  
Ion beam emittance 1.3 - 1.5 µm  
Proton beam emittance 2.2 µm  
Ion beam bunch length 0.09m depends on the blow up which will be set
Proton beam bunch length 0.09m depends on the blow up which will be set
RF voltage 14MeV  
β beating 3% from simulations; the same for both directions;
Peak lumi per bunch (head-on) 7.5x1026cm-2s-1 Initial lumi at IP1/5 with β*=0.6. Being optimistic could be a factor of 2 better.
IP1/5 (ATLAS/CMS)
β* 0.6  
Half crossing angle 140µrad  
Geometric Factor protons 0.739  
Geometric Factor ions 0.811  
Peak lumi estimate 3.9x1029cm-2s-1 Assuming 474 colliding bunches. Being optimistic could be a factor of 2 better.
IP2 (ALICE)
β* 2.0  
Geometric Factor protons 0.976  
Geometric Factor ions 0.985  
Peak lumi estimate 6.5x1028cm-2s-1 Assuming 216 colliding bunches. With optimisitic assumption could be higher by a factor of 2 in which case ALICE would be leveled to 1x1029. During the ramp up there will be less or no lumi to ALICE.
External crossing angle +138 µrad  
Internal crossing angle -75 µrad  
Total half crossing angle 63 µrad  
Magnet polarity + / +  
IP8 (LHCb)
β* 1.5  
External half-crossing angle -180µrad Was changed from -230µrad in order to gain aperture
Internal half-crossing angle -145µrad  
Net half-crossing angle IP2 -325µrad Was changed from -375µrad in order to gain aperture
Geometric Factor protons 0.598  
Geometric Factor ions 0.687  
Peak lumi estimate 4.4x1028cm-2s-1 Assuming 163 colliding bunches. With optimisitic assumption could be higher by a factor of 2.
Dipole polarity positive  

Filling schemes

Scheme  
100_200ns_702p_548Pb_474_216_163_20inj  
100_200ns_548Pb_702p_474_216_116_20inj  

This web site is owned by the account lpc .